+ 44 (0)20 8614 6200
info@corbett.co.uk
+ 44 (0)20 8614 6200
info@corbett.co.uk
Cornerstone Seminars
FIDIC
Knowledge Hub
+ 44 (0)20 8614 6200
info@corbett.co.uk

FIDIC 1999 Books – Commentary on Clause 8

Clause 8 contains all the fundamental provisions relating to the start of the Works, the Time for Completion, delays and the entitlement of the Contractor to an extension of time and of the Employer to delay damages, and finally the circumstances in which a suspension of the Works can occur and the implications for the Parties. 

By |November 14th, 2018|Delay, English Law, featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 8

Cherry Picking FIDIC 2017

Much has been said about the new Red, Yellow and Silver Books 2nd Editions launched by FIDIC in December last year. The most obvious comment has been about their size, almost 50,000 words, which is some 60% longer than the 1999 forms. Although the 1999 forms were not perfect, most regular users seem to be agreed that they did not need 20,000 words to fix the issues. This consensus led this author to attempt to cherry-pick the good bits from the 2017 forms and to propose amendments to add the good ideas to the 1999 forms. The amendments apply to all three forms unless it is indicated otherwise.

By |October 29th, 2018|Adjudication / Dispute Boards / ADR, Arbitration, Delay, Dispute Boards, Drafting, featured, Knowledge Hub|Comments Off on Cherry Picking FIDIC 2017

FIDIC 1999 Upgrade Launched

Corbett & Co. has published its selection of the best bits of the FIDIC 2017 2nd Editions adapted for use with the 1999 forms. With many people put off by the 50,000+ words of the new editions, the FIDIC 1999 Upgrade will permit users to benefit from FIDIC’s new ideas and improvements.

By |July 17th, 2018|featured, Knowledge Hub|Comments Off on FIDIC 1999 Upgrade Launched

Murphy’s Law

Earlier this year, the English High Court considered a heavily amended FIDIC Yellow Book 1999. Whilst the case is specific to the particular contractual amendments it is worth review. The case is J Murphy & Sons Ltd v Beckton Energy Ltd. It proceeded in court and on an expedited basis as a matter of some urgency because a bond was about to be called for non-payment of delay damages. The Contractor claimed the call would affect his commercial reputation, standing and creditworthiness, and may well need to be disclosed in future tenders. He had not paid the delay damages because there had been no agreement or determination of the entitlement to such by the Engineer under Sub-Clauses 2.5 and 3.5.

By |October 3rd, 2016|Bonds, Delay, English Law, Knowledge Hub|Comments Off on Murphy’s Law

FIDIC 1999 Books – Commentary on Clause 10

Clause 10 deals with the Taking-Over of the Works, Sections, or parts of the Works. Sub-Clause 10.1 deals with the Taking-Over of the Works and Sections. Taking-Over by the Employer happens when the Works (a) pass the Tests on Completion; (b) are substantially complete; (c) any contractual requirements relating to Taking-Over have been met; and (d) the Taking-Over Certificate has been issued or is deemed to have been issued. Sub-Clauses 10.2 and 10.3 deal with deemed Taking-Over where the Employer uses part of the Works or interferes with the Tests on Completion for more than 14 days. The failure to issue a Taking-Over Certificate by the Engineer, where the Employer has taken into commercial use the Works, will amount to a breach of contract.

By |August 1st, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 10

FIDIC 1999 Books – Commentary on Clause 2

Corbett & Co. has devised a helpful commentary on FIDIC 1999 books Clause 2. Clause 2 sets out certain obligations which are imposed on the Employer; however, this is by no means all the Employer’s obligations. The obligation to pay the Contractor, for example, is found in Sub-Clause 14.7 and the obligation to Take-Over the Works is found at Sub-Clause 10.1. The first obligation imposed on the Employer under this Clause is to give to the Contractor a right of access. Sub-Clause 2.1 needs to be read alongside Sub-Clauses 2.3 and 4.6, which make it clear that possession of the Site need not be exclusive. Sub-Clause 2.2 imposes on the Employer an obligation to assist the Contractor when requested to obtain permits, licences or approvals required by the laws of the Country. The obligation to reasonably assist is not an absolute obligation and generally will not mean the Employer will have to expend money on fulfilling the obligation. Sub-Clause 2.3 imposes on the Employer an obligation similar to that imposed on the Contractor under Sub-Clause 4.6. The Employer is responsible for any failure by its personnel to co-operate with the Contractor or to comply with safety regulations, take care of persons on Site, make sure the Site is reasonably free from unnecessary obstructions, and protect the environment. Sub-Clause 2.4 imposes on the Employer an obligation to show that financial arrangements have been made and are in place to enable it to pay the Contract Price. Sub-Clause 2.5 deals with the Employer’s Claims and requires that the Employer give notice and particulars of its claim before the Engineer makes a Determination under Sub-Clause 3.5. The Employer cannot set-off any claims it may have against the Contractor unless it complies with this Sub-Clause.

By |July 27th, 2016|Dispute Boards, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 2

FIDIC 1999 Books – Commentary on Clause 1

Clause 1 sets out many of the boilerplate clauses within the Contract and provides a number of definitions which are used thereafter. The Clause has been substantially changed from the Red Book 4th edn with a raft of new clauses added. Sub-Clause 1.3 deals with communications and states that approvals, certificates, consents and determinations shall not be unreasonable withheld or delayed. The assignment provisions in Sub-Clause 1.7 have now changed so that restriction on assignment applies to both the Contractor and Employer. Delayed Drawings and Instructions is dealt with at Sub-Clause 1.9. This was previously dealt with at Clause 6.4 of the Red Book 4th edn and it is unclear why such an important provision has now been rolled up in the General Provisions clause.

By |July 19th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 1
Go to Top