+ 44 (0)20 8614 6200
info@corbett.co.uk
+ 44 (0)20 8614 6200
info@corbett.co.uk
Cornerstone Seminars
FIDIC
Knowledge Hub
+ 44 (0)20 8614 6200
info@corbett.co.uk

FIDIC 2022 Reprints: 10 Key Areas Of Change In The FIDIC Red Book 2017

FIDIC ‘launched’ the FIDIC 2022 reprints at the FIDIC International Construction Users’ Conference 2022, in London. The reception to the changes was mixed – some embraced the clarity; others questioned the significance and cost. This article draws your attention to 10 of the key areas of change in respect of the FIDIC Red Book 2017 including the definition of Claim, matters to be agreed or determined, the definition of Dispute and Exceptional Events.

By |January 18th, 2023|Adjudication / Dispute Boards / ADR, Design, Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC 2022 Reprints: 10 Key Areas Of Change In The FIDIC Red Book 2017

FIDIC contracts—introduction to the FIDIC Green Book 2021

This Practice Note is an introduction to the FIDIC Green Book 2021 (the Short Form of Contract). It is not a fully detailed clause-by-clause commentary. This article was first published by LexisPSL

By |January 10th, 2023|Adjudication / Dispute Boards / ADR, Arbitration, Delay, Design, Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC contracts—introduction to the FIDIC Green Book 2021

FIDIC 1999 Books – Commentary on Clause 8

Clause 8 contains all the fundamental provisions relating to the start of the Works, the Time for Completion, delays and the entitlement of the Contractor to an extension of time and of the Employer to delay damages, and finally the circumstances in which a suspension of the Works can occur and the implications for the Parties. 

By |November 14th, 2018|Delay, English Law, featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 8

FIDIC 1999 Books – Commentary on Clause 14

Clause 14 deals with all aspects of payment.  It also deals with the Statement at Completion, the Final Payment Certificate, Discharge and Cessation of the Employer’s Liability. The Clause provides that this is a re-measurement contract and that the quantities stated in the Bill of Quantities are estimated.  There is provision for an advance payment to be made to the Contract.  Applications for Interim Payment Certificates are made monthly and these must be supported by documents and a report on progress.   Unless the amount assessed is less than the minimum amount set out in the Appendix to Tender, the Engineer has 28 days to issue an Interim Payment Certificate, which states the amount the Engineer fairly determines to be due.  The Employer thereafter has an obligation to pay the amount certified, in the currencies named in the Appendix to Tender.  In the event that payment is not received the Contractor can claim financing charges compounded monthly. Fifty per cent of the retention monies are paid when the Taking-Over Certificate is issued.  Where there are Sections then a proportion is paid.  The balance of retention is paid on the expiry of the latest Defects Notification Period or, where there are Sections, a proportion at the expiry of the Defects Notification Period for that Section.    Within 84 days of receiving the Taking-Over Certificate the Contractor submits a Statement at Completion.  This must include an estimate of all sums which the Contractor considers due. Within 56 days of receiving a Performance Certificate, the Contractor submits a Final Statement.  The Contractor must also submit with the Final Statement a written discharge which confirms that the total of the Final Statement represents full and final settlement of all moneys due.  The Engineer then issues to the Employer a Final Payment Certificate.  The Contract states that the Employer shall have no liability to the Contractor except to the extent that the Contractor has included an amount expressly for that matter in the Final Statement and also the Statement at Completion.

By |September 26th, 2018|featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 14

FIDIC 1999 Books – Commentary on Clause 10

Clause 10 deals with the Taking-Over of the Works, Sections, or parts of the Works. Sub-Clause 10.1 deals with the Taking-Over of the Works and Sections. Taking-Over by the Employer happens when the Works (a) pass the Tests on Completion; (b) are substantially complete; (c) any contractual requirements relating to Taking-Over have been met; and (d) the Taking-Over Certificate has been issued or is deemed to have been issued. Sub-Clauses 10.2 and 10.3 deal with deemed Taking-Over where the Employer uses part of the Works or interferes with the Tests on Completion for more than 14 days. The failure to issue a Taking-Over Certificate by the Engineer, where the Employer has taken into commercial use the Works, will amount to a breach of contract.

By |August 1st, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 10

FIDIC 1999 Books – Commentary on Clause 9

Clause 9 deals with the Tests on Completion. Sub-Clause 9.1 requires the Contractor to give notice when it is ready to carry out the Tests on Completion. Tests on Completion are a defined term at Sub-Clause 1.1.3.4. Sub-Clause 9.2 deals with delayed testing caused by either the Employer or the Contractor. Sub-Clause 9.3 deals with retesting after a failure to pass the Tests on Completion. Sub-Clause 9.4 deals with a failure to meet the requirements of the contract after retesting.

By |August 1st, 2016|Delay, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 9

FIDIC 1999 Books – Commentary on Clause 2

Corbett & Co. has devised a helpful commentary on FIDIC 1999 books Clause 2. Clause 2 sets out certain obligations which are imposed on the Employer; however, this is by no means all the Employer’s obligations. The obligation to pay the Contractor, for example, is found in Sub-Clause 14.7 and the obligation to Take-Over the Works is found at Sub-Clause 10.1. The first obligation imposed on the Employer under this Clause is to give to the Contractor a right of access. Sub-Clause 2.1 needs to be read alongside Sub-Clauses 2.3 and 4.6, which make it clear that possession of the Site need not be exclusive. Sub-Clause 2.2 imposes on the Employer an obligation to assist the Contractor when requested to obtain permits, licences or approvals required by the laws of the Country. The obligation to reasonably assist is not an absolute obligation and generally will not mean the Employer will have to expend money on fulfilling the obligation. Sub-Clause 2.3 imposes on the Employer an obligation similar to that imposed on the Contractor under Sub-Clause 4.6. The Employer is responsible for any failure by its personnel to co-operate with the Contractor or to comply with safety regulations, take care of persons on Site, make sure the Site is reasonably free from unnecessary obstructions, and protect the environment. Sub-Clause 2.4 imposes on the Employer an obligation to show that financial arrangements have been made and are in place to enable it to pay the Contract Price. Sub-Clause 2.5 deals with the Employer’s Claims and requires that the Employer give notice and particulars of its claim before the Engineer makes a Determination under Sub-Clause 3.5. The Employer cannot set-off any claims it may have against the Contractor unless it complies with this Sub-Clause.

By |July 27th, 2016|Dispute Boards, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 2

FIDIC 1999 Books – Commentary on Clause 1

Clause 1 sets out many of the boilerplate clauses within the Contract and provides a number of definitions which are used thereafter. The Clause has been substantially changed from the Red Book 4th edn with a raft of new clauses added. Sub-Clause 1.3 deals with communications and states that approvals, certificates, consents and determinations shall not be unreasonable withheld or delayed. The assignment provisions in Sub-Clause 1.7 have now changed so that restriction on assignment applies to both the Contractor and Employer. Delayed Drawings and Instructions is dealt with at Sub-Clause 1.9. This was previously dealt with at Clause 6.4 of the Red Book 4th edn and it is unclear why such an important provision has now been rolled up in the General Provisions clause.

By |July 19th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 1
Go to Top