+ 44 (0)20 8614 6200
info@corbett.co.uk
+ 44 (0)20 8614 6200
info@corbett.co.uk
Cornerstone Seminars
FIDIC
Knowledge Hub
+ 44 (0)20 8614 6200
info@corbett.co.uk

FIDIC 1999 Books – Commentary on Clause 3

Clause 3 deals with the duties and obligations of the Engineer and his assistants.  Sub-Clause 3.1 deals with the role and duties of the Engineer.  The Engineer is deemed to act for the Employer.  The Engineer has no authority to relieve the Contractor of his duties, obligations or responsibilities under the Contract; nor can the Engineer amend the Contract. Under Sub-Clause 3.2 the Engineer can delegate authority to any assistants; however, the Engineer cannot delegate the responsibility to make Determinations.  Under Sub-Clause 3.3 the Engineer may issue instructions or modified Drawings at any time, which are necessary for the execution of the Works.  If the instruction constitutes a Variation, then it is dealt with under Clause 13 [Variations and Adjustments].  The Contractor is required to comply with any instruction given by the Engineer or delegated assistant.  Sub-Clause 3.4 deals with the replacement of the Engineer.  The Employer must not replace the Engineer with someone against whom the Contractor raises reasonable objection. Sub-Clause 3.5 deals with Determinations.  When making a Determination the Engineer should consult with each of the Parties and, if agreement cannot be reached, make a fair determination in accordance with the Contract, taking due regard of all relevant circumstances.  Both Parties are required to give effect to any Determination unless, or until, it is revised under Sub-Clause 20.1 [Claims, Disputes and Arbitration].

By |September 26th, 2018|Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 3

FIDIC 1999 Books – Commentary of Clause 11

Clause 11 requires that the Works shall be in the condition required by the Contract at the end of the Defects Notification Period. Where the Contractor carries out work in the Defects Notification Period, it is not entitled to receive payment if the work was a result of a defect in the design for which the Contractor was responsible. Similarly, if the Plant, Materials or workmanship are not in accordance with the Contract or there is a failure by the Contractor to comply with any other obligation then it is required to remedy the problem without payment. The Employer may obtain an extension of the Defects Notification Period if the Works, a Section or a major piece of Plant cannot be used during the Defects Notification Period. The Contractor is required to remedy any defect during the Defect Notification Period and, if it does not, the Employer may claim against the Contractor. Rights are given to the Contractor to undertake this work subject to the Employer’s reasonable security restrictions. Once the Defects Notification Period has expired the Engineer is required within 28 days, subject to receipt of the Contractor’s Documents and the completion of any tests, to issue a Performance Certificate. It is the Performance Certificate that is deemed to constitute acceptance of the Works. Sub-Clause 11.10 provides that after the Performance Certificate has been issued, each Party will remain liable for the fulfilment of any obligation which remains unperformed at the time. The extent and meaning of this clause is open to debate.

By |August 11th, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary of Clause 11

FIDIC 1999 Books – Commentary on Clause 10

Clause 10 deals with the Taking-Over of the Works, Sections, or parts of the Works. Sub-Clause 10.1 deals with the Taking-Over of the Works and Sections. Taking-Over by the Employer happens when the Works (a) pass the Tests on Completion; (b) are substantially complete; (c) any contractual requirements relating to Taking-Over have been met; and (d) the Taking-Over Certificate has been issued or is deemed to have been issued. Sub-Clauses 10.2 and 10.3 deal with deemed Taking-Over where the Employer uses part of the Works or interferes with the Tests on Completion for more than 14 days. The failure to issue a Taking-Over Certificate by the Engineer, where the Employer has taken into commercial use the Works, will amount to a breach of contract.

By |August 1st, 2016|Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 10

FIDIC 1999 Books – Commentary on Clause 9

Clause 9 deals with the Tests on Completion. Sub-Clause 9.1 requires the Contractor to give notice when it is ready to carry out the Tests on Completion. Tests on Completion are a defined term at Sub-Clause 1.1.3.4. Sub-Clause 9.2 deals with delayed testing caused by either the Employer or the Contractor. Sub-Clause 9.3 deals with retesting after a failure to pass the Tests on Completion. Sub-Clause 9.4 deals with a failure to meet the requirements of the contract after retesting.

By |August 1st, 2016|Delay, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 9

FIDIC 1999 Books – Commentary on Clause 2

Corbett & Co. has devised a helpful commentary on FIDIC 1999 books Clause 2. Clause 2 sets out certain obligations which are imposed on the Employer; however, this is by no means all the Employer’s obligations. The obligation to pay the Contractor, for example, is found in Sub-Clause 14.7 and the obligation to Take-Over the Works is found at Sub-Clause 10.1. The first obligation imposed on the Employer under this Clause is to give to the Contractor a right of access. Sub-Clause 2.1 needs to be read alongside Sub-Clauses 2.3 and 4.6, which make it clear that possession of the Site need not be exclusive. Sub-Clause 2.2 imposes on the Employer an obligation to assist the Contractor when requested to obtain permits, licences or approvals required by the laws of the Country. The obligation to reasonably assist is not an absolute obligation and generally will not mean the Employer will have to expend money on fulfilling the obligation. Sub-Clause 2.3 imposes on the Employer an obligation similar to that imposed on the Contractor under Sub-Clause 4.6. The Employer is responsible for any failure by its personnel to co-operate with the Contractor or to comply with safety regulations, take care of persons on Site, make sure the Site is reasonably free from unnecessary obstructions, and protect the environment. Sub-Clause 2.4 imposes on the Employer an obligation to show that financial arrangements have been made and are in place to enable it to pay the Contract Price. Sub-Clause 2.5 deals with the Employer’s Claims and requires that the Employer give notice and particulars of its claim before the Engineer makes a Determination under Sub-Clause 3.5. The Employer cannot set-off any claims it may have against the Contractor unless it complies with this Sub-Clause.

By |July 27th, 2016|Dispute Boards, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 2
Go to Top