+ 44 (0)20 8614 6200
info@corbett.co.uk
+ 44 (0)20 8614 6200
info@corbett.co.uk
Cornerstone Seminars
FIDIC
Knowledge Hub
+ 44 (0)20 8614 6200
info@corbett.co.uk

FIDIC 1999 Books – Commentary on Clause 6

Clause 6 deals with Staff and Labour. These provisions need to be read with the applicable laws where the works are being carried out or the relevant employment law if different. Sub-Clause 6.1 commits the Contractor (unless otherwise specified) to pay for his staff and their housing feeding and transport. Sub-Clause 6.2 requires the Contractor not to pay lower wages or give lower conditions than those generally applicable locally. Sub-Clause 6.3 forbids the Contractor from attempting to recruit from the Employer’s Personnel. Sub-Clause 6.4 requires the Contractor to abide by labour laws and to require his staff to obey the law generally. Sub-Clause 6.5 forbids work on locally recognised rest days or outside the working hours set out in the Appendix to Tender, unless stated in the Contract or agreed to by the Engineer or essential for the protection of life or property or for safety reasons. Sub-Clause 6.6 requires the Contractor to provide and maintain all necessary accommodation for its personnel and for the Employer’s personnel to the extent stated in the Specification. It is forbidden from permitting its own Personnel from living within the structures forming part of the Permanent Works. Sub-Clause 6.7 requires the Contractor to maintain the health and safety of its personnel and maintain proper medical facilities for its own personnel and for any Employer Personnel accommodated. It is required to appoint an accident prevention officer. It is required to notify the Employer of any accidents and maintain records. Sub-Clause 6.8 requires the Contractor to provide all necessary superintendence by a sufficient number of properly qualified people with adequate knowledge of the defined language of communications. Sub-Clause 6.9 requires the Contractor to ensure that its personnel are properly qualified, skilled and experienced. The Employer may require the Contractor to remove any person employed on the Site or the Works who commits misconduct, is incompetent or negligent, fails to perform in accordance with any provision of the Contract or persists in any conduct prejudicial to health, safety or the environment. If a person is removed the Contractor will have to replace him. Sub-Clause 6.10 requires the Contractor to submit to the Engineer details showing personnel and equipment on Site. This is required each month and must be in a form approved by the Engineer. Sub-Clause 6.11 requires the Contractor to take reasonable precautions to prevent disorderly conduct by Contractor’s Personnel and to preserve the peace and protection or nearby persons and property.

By |November 14th, 2018|featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 6

FIDIC 1999 Books – Commentary on Clause 3

Clause 3 deals with the duties and obligations of the Engineer and his assistants.  Sub-Clause 3.1 deals with the role and duties of the Engineer.  The Engineer is deemed to act for the Employer.  The Engineer has no authority to relieve the Contractor of his duties, obligations or responsibilities under the Contract; nor can the Engineer amend the Contract. Under Sub-Clause 3.2 the Engineer can delegate authority to any assistants; however, the Engineer cannot delegate the responsibility to make Determinations.  Under Sub-Clause 3.3 the Engineer may issue instructions or modified Drawings at any time, which are necessary for the execution of the Works.  If the instruction constitutes a Variation, then it is dealt with under Clause 13 [Variations and Adjustments].  The Contractor is required to comply with any instruction given by the Engineer or delegated assistant.  Sub-Clause 3.4 deals with the replacement of the Engineer.  The Employer must not replace the Engineer with someone against whom the Contractor raises reasonable objection. Sub-Clause 3.5 deals with Determinations.  When making a Determination the Engineer should consult with each of the Parties and, if agreement cannot be reached, make a fair determination in accordance with the Contract, taking due regard of all relevant circumstances.  Both Parties are required to give effect to any Determination unless, or until, it is revised under Sub-Clause 20.1 [Claims, Disputes and Arbitration].

By |September 26th, 2018|Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC 1999 Books – Commentary on Clause 3

FIDIC 2017 Books – Clause 3 – The Engineer

The main changes: Employer’s consent and neutrality The main changes in Clause 3 are the express provisions in Sub-Clause 3.2 [Engineer’s Duties and Authority] that the Engineer is not required to obtain the Employer’s consent before the Engineer exercises its authority under Sub-Clause 3.7 [Agreement or Determination], and that the Engineer must act “neutrally” when exercising its duties under Sub-Clause 3.7 [Agreement or Determination].  Dictionary definitions suggest that “neutrally” is similar in meaning to the words “independently” or “impartially” found in the FIDIC Red Book 4th edition and the FIDIC Yellow Book 3rd edition. However, the drafting committee believe that by using a different word it will avoid the difficulties raised in the interpretation of independently or impartially in the earlier editions.  This remains to be seen.  The intention is that “the Engineer treats both Parties even-handedly, in a fair minded and unbiased manner”.

By |January 27th, 2018|Knowledge Hub|Comments Off on FIDIC 2017 Books – Clause 3 – The Engineer

FIDIC 2017 – First Impressions of the 3-Kilo Suite

In London last week, FIDIC launched its Second Editions of the Red, Yellow and Silver Books. They are big, weighing in at almost a kilo each. The general conditions cover 106 pages with more than 50,000 words, over 50% longer than the 1999 forms. Many improvements have been made, addressing issues that have emerged since 1999. Fans of Dispute Boards will be pleased to see that all three books now have standing boards with more emphasis on dispute avoidance; and that appointment of DB members and enforcement of their decisions have been made easier. Disputes and Arbitration are now dealt with in a separate chapter 21. Here are the most interesting changes to the Yellow Book.

By |December 13th, 2017|Dispute Boards, featured, Knowledge Hub|Comments Off on FIDIC 2017 – First Impressions of the 3-Kilo Suite

The Employer’s Agent

The Engineer is deemed to act for the Employer and is essentially the Employer’s agent under the FIDIC Red Book 1999. He is not a wholly impartial intermediary, unless such a role is specified in the Particular Conditions, and there is no general obligation under the FIDIC Red Book 1999 for the Engineer to act independently or impartially. However, when he is required to make a determination under Sub-Clause 3.5, he is obliged to make it a fair determination and when he is obliged to issue an Interim Payment Certificate under Sub-Clause 14.6, or a Final Payment Certificate under Sub-Clause 14.13, he must fairly determine the amount due.

By |February 8th, 2017|featured, Knowledge Hub|Comments Off on The Employer’s Agent
Go to Top